Brook Road Bridge

2024

  • June 24, 2024 Update: The Brook Road Bridge Construction Project is now complete. The bridge is now open to all vehicular and pedestrian traffic,
  • Construction began the week of March 4, 2024.  Normal working hours are 7:00 a.m. to 4:00 p.m. Monday – Friday, during which time various equipment, machinery, and materials will be in the roadway. No work is anticipated to occur on weekends or holidays. 

2023

  • March 3, 2023 Update:  MassDOT approved the use of existing Small Bridge Grant Funds for the design and construction of the proposed remediation of the Brook Road Bridge.  
  • Project went out to bid in November 2023 and was awarded to MAS Building and Bridge, Inc.

2022

  • On Tuesday, June 28, 2022 Howard Stein Hudson will be presenting the results of their structural analysis to the Select Board. See Howard Stein Hudson's June 21, 2022 Technical Memorandum (PDF).